And the winner is…

We received five bids today. Here they are:

The low bidder will have to be vetted by the city and they have 24 hours to retract their bid if there is an error. I guess we’ll see on Monday when we meet to go over the bid documents.

BidsAwards
Company Bid Bid Amount Award Award Amount Comment
A-1 Landscaping and Construction, Inc.
20607 State Route 9 SE
Snohomish, WA 98296
$224,000.00
Construct Co.
1621 Pease Ave
Sumner, WA 98390
$295,000.00
iliad inc
po box 20098
seattle, WA 98102
$134,706.00
PJM Construction
610 West Smith Street
Seattle, WA 98119
$134,500.00
WS Contractors
28707 210th Ave SE
Kent, WA 98042
$117,950.00

Posted on June 4th 2008 by David Folweiler in Misc. | 2 Comments So Far |

2 Comments on “And the winner is…”

  1. cshawjones Says:

    Since the bottom three bids are within a fairly narrow $ range, shouldn’t all three be reviewed and factored in with references, quality of work, etc.

    I have never understood why the absolute lowest bid gets the job even if it’s not the best qualified company.

    In my career, I’ve seen vendors bid low, be accepted, and then have to be replaced, ultimately costing more than if a bit more due diligence was done and money spent up front.

  2. david Says:

    cshawjones –

    I’m agree with your thoughts. I’d like to be able to consider all sorts of variables, but I understand that the city is bound by law to accept the low bidder, except in cases where they are extremely unsuitable.

    I’m hoping that all will go smoothly.